ADMINISTRATIVE HOUSE BUILDING IN KIEV REGION

Focus
Foundation of the building
Location
Petrovskoe village, Kiev region
YEAR
2014 y.
TECHNOLOGY
DEEP Lifting

In June 2014, the soils were stabilized at the base of the foundations of the outer and inner walls of the two-story administrative building.

The reason for petition
Numerous horizontal, vertical, inclined cracks in brick walls and partitions; upsetting floor slabs of the first floor in separate rooms up to 15 mm.

Problem
Soil moisture. Heterogeneity of the soil.
The reasons for the softening of the soil were leaks from water pipes located in the immediate vicinity of the foundations.

Work done
— soil stabilization at the base of the foundations of external and internal walls;
— raising the floor slab to the design mark.

Applicable Methods
Deep Lifting

Scope of work
74.6 m.p. strip foundations.

The work was performed without stopping the operation of the building.

If you didn’t find an object or a situation similar to yours in the portfolio on the website, then order a specialist to select a project to analyze the pros and cons of technologies from the extensive database of completed GeoResin projects.
Back to projects
Leave a comment or ask a question
Standard projects and cost
Leave a comment
Comments
Thank you for your comment!
Close

Leave your phone number and our consultant will contact you

Choose a convenient time to call

Leave your email and we will send you this article

  • Services
  • Technologies
  • Portfolio
  • Video
  • Technoblog
  • About us
  • Contacts
  • GeoResin