ua
ru
en

We work throughout Ukraine

AUTOCENTER BUILDING IN OBOLONSKY DISTRICT OF KIEV

Focus
Foundation
Location
Kiev, Ukraine
YEAR
2015 y.
TECHNOLOGY
DEEP Lifting

The building of the car center in the Obolonsky district of Kiev.

The reason for petition
Numerous cracks in the walls and partitions; upsetting of the floor plate of the first floor in separate rooms. For a short time, cracks increased and new ones appeared.

Problem
The voids under the floor slab. The settlement of the foundations of columns and brick walls. The reasons for the sediment were - the impact of groundwater, leaks from the intake pits, heterogeneous bulk soil with the content of construction waste in the base of the foundations.

Work done
— soil stabilization at the base of columnar foundations, foundation beams and strip foundations;
— the rise of self-supporting brick walls to close cracks;
— filling voids under the floor slab;
— soil stabilization at the base of the floor slab.

Applicable Methods
Deep Lifting, Floor Lifting.

Scope of work
The work was carried out in a part of the building with an area of 330 m2.

The work was performed without stopping the operation of the building.

If you didn’t find an object or a situation similar to yours in the portfolio on the website, then order a specialist to select a project to analyze the pros and cons of technologies from the extensive database of completed GeoResin projects.
Back to projects
Leave a comment or ask a question
Standard projects and cost
Leave a comment
Comments
Thank you for your comment!
Close

Leave your phone number and our consultant will contact you

Choose a convenient time to call

Leave your email and we will send you this article

  • Services
  • Technologies
  • Portfolio
  • Video
  • Technoblog
  • About us
  • Contacts
  • GeoResin